GARID Flood-Control Projects Stalled as Ministry Awaits Financial Clearance 

By Godwill Arthur-Mensah, GNA 

Accra, Nov. 19, GNA – Major flood-control interventions designed to reduce the perennial flooding menace in Accra are yet to take off, as government awaits financial authorisation from the Ministry of Finance. 

The awaiting financial authorisation would award contracts and begin construction works under the Greater Accra Resilient and Integrated Development (GARID) Project. award contracts and begin construction works under the Greater Accra Resilient and Integrated Development (GARID) Project. 

The six projects, which form part of efforts to strengthen the capital’s resilience to flooding and climate-related risks, are currently at the tendering and contract award stage. 

Mr Ahmed Ibrahim, Minister of Works, Housing and Water Resources, disclosed this when answering questions on the floor of Parliament on Wednesday, November 18,2026. 

The projects include the reconstruction of the Abbosey Okai Bridge, construction of the Atomic East and West detention ponds, improvement works on the Alajo drain, repackaged works on the Nima drain, and the installation of the Accra Flood Early Warning Systems. 

Mr Ibrahim said the commencement of the projects was subject to the granting of the required commitment authorisation by the Ministry of Finance. 

He noted that the World Bank-funded GARID Project was implementing both structural and non-structural flood mitigation measures using a basin-wide approach focused on the Odaw Basin. 

The Minister said the Nima-Paloma drainage project contract had been terminated and would be repackaged and re-awarded to a new contractor once the necessary financial commitment had been secured. 

He said progress at the time of termination stood at 13 per cent for evacuation of works, 25 per cent for demolition of the existing drain, 9.7 per cent for casting of the concrete base, and 9.5 per cent for casting of concrete walls. 

Mr Ibrahim said the Ministry had engaged Messrs Dredge Masters to desilt the Nima-Paloma drain to improve the conveyance of stormwater while awaiting financial clearance to continue the project. 

“Further, some additional local measures were put in place to reduce the exposure of adjoining communities at the upstream and downstream sections of the Nima drain where the previous contractor had initiated works but had not completed,” he said. 

The Minister said the Ministry was also engaging relevant stakeholders, including the World Bank, to determine the most appropriate procurement arrangement for engaging a new contractor to complete the project. 

GNA 

Edited by Linda Asante Agyei