Accra, June 21, GNA – The Board of Directors of the African Development Bank (AfDB) has approved a $23.04 million loan to Prime Meridian Docks AssetCo Ltd (PMD) for the construction of a modern floating dock facility.

It is a special purpose entity to co-finance the construction of a dock ship repair facility at Ghana’s western Takoradi port.

The loan will support the company to design, build, operate and maintain a world-class ship repair and maintenance facility in the Gulf of Guinea under a 25-year concession granted to the company by the Ghana Ports and Harbours Authority.

A statement issued in Accra said the project, estimated to cost $137 million, would involve constructing a 200-meter jetty, dredging 300,000 cubic meters of rock in the port basin, and procuring and installing a 13,500-tonne lift capacity floating dock.

The facility will also have offices, a warehouse, mechanical workshops for steel and pipe fabrication, electrical works, blasting and painting, and equipment maintenance.

The statement said the Board also authorised a syndication on a “best efforts basis” of additional financing of up to $11 million.

Mr Mike Salawou, Director for Infrastructure, Cities and Urban Development at the Bank, said: “Vessel repair and maintenance is an underserved market on the continent. Investing in it will provide a more holistic approach to supporting maritime transport and its sustainability, which will accelerate regional integration and attract international trade and economic activity.”

PMD is a Ghanaian company founded and headed by Mr. Stanley Raja Korshie Ahorlu, sponsor of the project.

Mr Ahorlu said the Bank’s approval of the facility is a “culmination of many years of dedication and commitment and an endorsement of PMD’s drive to transform Africa’s maritime sector”.

The Bank’s hard currency long-term financing for the project will enable it to create over 400 permanent jobs – 15 per cent of, which are expected to go to women.

It said that was significantly above the global average of two per cent in the maritime sector.

The construction of the floating dock will enhance the resilience of the ocean economy in Ghana and mitigate the carbon footprint from an expected increase in vessel flow, promoting the use of renewable energy, energy efficiency and slow vessel steaming.

This aligns with the International Maritime Organization’s best practices and Ghana’s Nationally Determined Contributions, making the project Paris Aligned.

The project aligns with the Bank’s Country Strategy Paper for Ghana (2019-2023) to increase private sector investment in the real sector.

It contributes to job creation, bridging inequality gaps and supports the overall macroeconomic stability in Ghana while mainstreaming various crosscutting issues into the Bank’s interventions.

The project also aligns with the national ambition of Ghana to become a hub for shipping and petroleum operations in West Africa.

The statement said by enhancing the supply of maritime maintenance and repair services, the project would help minimise transport and logistic costs and time, resulting in increased mobility and connectivity and boosting Ghana’s competitiveness.

It said skills transfer was a significant development outcome of the project.

The project’s operations/technical and commercial management operator will train staff in its Aberdeen Training Institute, and a partnership will be developed with the Regional Maritime University in Tema, Ghana, throughout the project’s life.